Buckland Park - 'Riverlea' (Township)

The proposal

Buckland Park is proposed as a country township by Walker Corporation Pty Ltd and Day Corporation Pty Ltd. It consists of 12,000 dwellings on a 1,340 hectare site, between Virginia and Port Gawler.

The proposal comprises:

  • a town centre
  • shopping and commercial facilities
  • a medical centre
  • schools
  • community and recreation facilities.

Background

In January 2007, the Buckland Park Township development (now known as ‘Riverlea’) undertaken by the Walker Corporation was declared a Major Development under Section 46 of the former Development Act 1993 by the then Minister for Urban Development and Planning.

On 4 February 2010, following an Environmental Impact Statement (EIS) process the project received a provisional Development Authorisation from the then Governor of South Australia.

The development is based on an approved Master Plan to be staged over a 25-year period, which at completion would accommodate approximately 12,000 residential allotments and a resident population of 30,000 people. The development will also include schools, shopping centres, parks, employment areas, and mixed-use precincts.

Following completion of reserve matter requirements, full Development Authorisation for Stage 1 was provided on 3 July 2014, at which time Stage 1 (600 allotments and associated retail area) was renamed Precinct 1 and included 5 stages.

On 12 February 2017, Precincts 2 and 2C, with approximately 2,500 additional allotments, were granted a full Development Authorisation.

A number of variations have been approved to refine the final configuration of staging, allotments, public roadways, reserve areas, with new allotments now created and construction works underway.

The developer has now sought a further variation to their current development authorisation, in the form of an amendment to the EIS.

The proposed changes involve a revised stormwater and flood mitigation strategy comprising a saltwater lake system, a revised road network pattern, land division layout and staging plan, and related infrastructure for Precinct 2.

Assessment stages and documentation

Stage

Date

Documentation

Minister’s Decision

Pending

 

Assessment Report

Pending

 

Response Document

Pending

 

Amendment to the Environmental Impact Statement

14 June 2023

Amendment - Precinct 2 and Stage 11, 12A, 12B, 40 and 4128 April 2023Decision Notification (PDF, 340 KB)
Amendment - Precinct 2 and Stage 9a28 April 2023Decision Notification (PDF, 342 KB)
Amendment - Precinct 1 and Stage 4 and 10b and retail site4 August 2022Decision Notification (PDF, 7047 KB)
Amendment - Precinct 2 and Stage 10, 10a and 113 August 2022Decision Notification (PDF, 1232 KB)

Amendment - Precinct 1 and Stage 4

21 March 2022

Decision Notification (PDF, 1250 KB)

Amendment - Precinct 2 (staging) and Stage 818 February 2022Decision Notification (PDF, 1831 KB)

Amendment - Precinct 1 and Stage 7

11 January 2022

Decision Notification (PDF, 17333 KB)

Amendment - Precinct 1 (Stages 2 & 3) and Display Village

16 June 2021

Government Gazette dated 24 June 2021

Condition 54 (Intersection works)

4 February 2021

Government Gazette dated 11 February 2021

Precinct 1 (Stages 1-6) Amendment (Delegate)

1 October 2020

Government Gazette dated 1 October 2020

Extension of time (Delegate)

11 April 2019

Government Gazette dated 11 April 2019

Governor's Decision for new Superlot Plan, Precinct 2 and 2C, and Road Closure of part of Buckland Park Road

17 October 2017

Government Gazette dated 17 October 2017

Governor's Decision for Precinct 2 and 2C

16 February 2017

Government Gazette dated 16 February 2017

Assessment Report for Precinct 2 and 2C

16 February 2017

Assessment Report (PDF, 16568 KB)

Extension of Time (Delegate)

16 October 2016

 

Extension of Time (Delegate)

29 October 2015

Government Gazette dated 29 October 2015

Precinct One Amendment (Delegate)

5 March 2015

Government Gazette dated 5 March 2015

Amendment to Environmental Impact Statement

4 March 2015

Amendment EI Statement (PDF, 29213 KB)

Advertisement of EIS change (PDF, 35 KB)

CEMMP / SWP (Delegate)

20 June 2014

 

Precinct One (Delegate)

3 July 2014

Government Gazette dated 3 July 2014

Wastewater Facility (Governor)

23 December 2013

Government Gazette dated 23 December 2013

Purple Pipes (Delegate)

24 January 2013

Government Gazette dated 24 January 2013

Reserved Matters (Delegate)

22 December 2011

Government Gazette dated 22 December 2011

Reserved Matters (Delegate)

15 September 2011

Government Gazette dated 15 September 2011

Reserved Matters (Delegate)

10 March 2011

Government Gazette dated 10 March 2011

Amended Gazette Notice (Delegate)

21 October 2010

Government Gazette dated 21 October 2010

Governor's decision

4 February 2010

Government Gazette dated 4 February 2010

Assessment report by Minister

4 February 2010

BPT Assessment Report (PDF, 6373 KB)

BPT Advert - Buckland Park Assessment Report (PDF, 32 KB)

Response by proponent to public and agency comment on assessment document

4 February 2010

BPT Response Report Report (PDF, 7486 KB)

BPT Response Report Appendices (PDF, 29188 KB)

Release of environmental impact statement document by proponent for public and agency comment

4 May 2009

The environmental impact statement was released for a six week public comment period from 4 May 2009 to 15 June 2009

Written submissions commenting on the EIS were invited until 15 June 2009

A public meeting was held at the Virginia Horticulture Centre on 13 May 2009

BPT Advert - Buckland Park EIS (PDF, 48 KB)

BPT Environmental Impact Statement (PDF, 10705 KB)

Note: Appendix 1 has not been included. It contains figures which are within the environmental impact statement report chapters.

BPT Environmental Impact Statement Appendix 2 to 7 (PDF, 28118 KB)

BPT Environmental Impact Statement Appendix 8 (PDF, 27141 KB)

BPT Environmental Impact Statement Appendix 9 (PDF, 38184 KB)

BPT Environmental Impact Statement Appendix 10 to 13 (PDF, 28256 KB)

BPT Environmental Impact Statement Appendix 14 to 18 (PDF, 29321 KB)

BPT Environmental Impact Statement Appendix 19 (PDF, 8114 KB)

BPT Environmental Impact Statement Appendix 20 to 23 (PDF, 35490 KB)

BPT Environmental Impact Statement Appendix 24 (PDF, 6435 KB)

BPT Environmental Impact Statement Appendix 25 to 27 (PDF, 3662 KB)

Release of guidelines for an environmental impact statement as determined by the Development Assessment Commission with level of assessment determined

Revised guidelines 17 September 2008

BPT Advert: Amended Buckland Park EIS Guidelines - Sep 2008 (PDF, 37 KB)

Revised Environmental Impact Statement Guidelines (PDF, 2521 KB) (17 September 2008)

BPT Original Environmental Impact Statement Guidelines (PDF, 565 KB) (issued 19 September 2007)

Declaration as major development

4 January 2007

Government Gazette dated 4 January 2007

Variation to declaration - Government Gazette dated 12 June 2008. (Revised declaration increases size of subject area from 100 hectares to 1,400 hectares and includes assessment of neighbourhood centre).